Hoffman-Boston Elementary HVAC and roof replacement
HVAC modernization and roof replacement with ceilings, lighting, and interior finishes in affected areas. School Board-approved project budget $45.65M; completion anticipated Fall 2028.
The short answer
- Where it stands
- Project development and design. Completion anticipated Fall 2028
- Who decides next
- APS Facilities and Operations
- Your next move
- No dated venue is open right now. Public comment at any School Board meeting still applies.
683 days
until APS Facilities and Operations decide, Sep 1, 2028
Where it is
APS Approved FY 2027-36 Capital Improvement Plan (CIP)
Arlington Public Schools
Retrieved 2026-09-24
Adopted June 18 2026; report dated August 2026; Appendix C funding timeline is an image (not read)
- DoneCIP direction
- DoneSuperintendent's proposed CIP
- DoneCIP adoption and bond request
- DoneCounty Board resolution and court-ordered election
- DoneBond referendum
- NowProject development and design
- Step 7Construction
- Done CIP direction
- Done Superintendent's proposed CIP
- Done CIP adoption and bond request
- Done County Board resolution and court-ordered election
- Done Bond referendum
- Now Project development and design
- Step 7 Construction
Why this track: Funded through earlier bonds and the adopted CIP. The CIP gives a budget and a completion date but does not say whether design or construction is under way today.
APS Approved FY 2027-36 Capital Improvement Plan (CIP)
Arlington Public Schools
Retrieved 2026-09-24
Adopted June 18 2026; report dated August 2026; Appendix C funding timeline is an image (not read)
What happens next
- Jun 18, 2026
APS Approved FY 2027-36 Capital Improvement Plan (CIP)
Arlington Public Schools
Retrieved 2026-09-24
Adopted June 18 2026; report dated August 2026; Appendix C funding timeline is an image (not read)
Adopted CIP carries the School Board-approved $45.65M project budget
School Board · School Board meeting
- Sep 1, 2028Next
APS Approved FY 2027-36 Capital Improvement Plan (CIP)
Arlington Public Schools
Retrieved 2026-09-24
Adopted June 18 2026; report dated August 2026; Appendix C funding timeline is an image (not read)
Completion anticipated Fall 2028
APS Facilities and Operations · Site
- Cost
- $45.65M (School Board-approved project budget)
APS Approved FY 2027-36 Capital Improvement Plan (CIP)
Arlington Public Schools
Retrieved 2026-09-24
Adopted June 18 2026; report dated August 2026; Appendix C funding timeline is an image (not read)
- Window
- Completion anticipated Fall 2028
APS Approved FY 2027-36 Capital Improvement Plan (CIP)
Arlington Public Schools
Retrieved 2026-09-24
Adopted June 18 2026; report dated August 2026; Appendix C funding timeline is an image (not read)
123 days since the first public step. 683 days until the planned finish. The filled part of the bar, 15%, is behind us.
- $45.65MSchool Board-approved project budget
APS Approved FY 2027-36 Capital Improvement Plan (CIP)
Arlington Public Schools
Retrieved 2026-09-24
Adopted June 18 2026; report dated August 2026; Appendix C funding timeline is an image (not read)
Who decides
Decides the current step
School Board
Project development and design · School Board meetings (approves at design milestones)
Decides the next step
APS Facilities and Operations
Construction · Site
From the Capital Improvement Plan track, verification: Documented, not yet confirmed.
Where to engage
Regular meetings, generally 7 p.m. at the Syphax Education Center
Online speaker form opens four business days before and closes 4 p.m. the day before; max 30 speakers x 2 minutes
School Board meeting, Oct 8, 2026
Passed Oct 7, 2026Thursday, 7 p.m., Syphax Education Center, 2110 Washington Blvd
Sign up to speak: the online form opens Oct 2 and closes Oct 7 at 4 p.m.
What to ask
“Is the Hoffman-Boston HVAC and roof project in design or in construction today, and which classrooms will be affected in which school year?”
School Board Meetings (2026-27 dates)
Arlington Public Schools
Retrieved 2026-09-24
Lists Oct 8, Oct 22, Nov 12 2026; 7 p.m. at Syphax unless noted
What has been asked
- Open questionfor APS Facilities and OperationsNot yet asked
Is the Hoffman-Boston project in design or in construction today?
The CIP gives a budget and a Fall 2028 completion but not the current stage.
Source: APS Approved FY 2027-36 Capital Improvement Plan (CIP)